Marshalltown HMA Street Rehab Project continues

Street Rehab Work is in full swing. If the weather can hold out for the next week, the City is anticipating a significant amount of work between now and July 13.

Below is the goal of where crews are headed next:

• Quadrant 1, Group A:

West State Street from North 13th Street to North Fifth Street (Ward 2)

Asphalt – Interlayer Lift – July 6-9

• Quadrant 1, Group B:

North Second Street from West State Street to West Lincoln Street (Ward 1)

West Webster Street from North Second Street to North Center Street (Ward 1)

West Grant Street from North Second Street to North Center Street (Ward 1)

Asphalt – Interlayer Lift – July 8-9

• Quadrant 1, Group C

South First Street from West Boone Street to West Church Street (Ward 1)

South First Street from West Madison Street to West Boone Street (Ward 3)

West Linn Street from South Third Street to South First Street (Ward 1)

Asphalt – Interlayer Lift – Completed

• Quadrant 1, Group D

South Fourth Street from West Main Street to West Nevada Street (Wards 1, 2, & 3)

South Fifth Street from West Main Street to West Nevada Street (Wards 2 & 3)

West Nevada Street from South Sixth Street to South Third Street (Ward 3)

Milling / Patching – July 9

Asphalt – Interlayer Lift – July 9-10

• Quadrant 2, Group A

East Boone Street from South 12th Avenue Place to South 14th Avenue (Ward 1)

South 14th Avenue from East Nevada Street to East Linn Street (Ward 1)

Asphalt – Interlayer Lift – July 10-13

• Quadrant 2, Group B

South 16th Avenue from East Nevada Street to Norris Place (Ward 1)

Norris Place from South 16th Avenue to South 17th Avenue (Ward 1)

South 17th Avenue from Norris Place to East Linn Street (Ward 1)

Asphalt – Interlayer Lift – July 10-13

• Quadrant 3 – Full Depth

South First Avenue from South Street to Ferner Street (Ward 4)

This section is a full depth mill and asphalt.

This is underway and will continue for a few days, July 6-8.

• Quadrant 3

East Ferner Street from South Center Street to South Second Avenue (Ward 4)

South First Avenue from East Anson Street to East Ingledue Street (Ward 4)

West Ingledue Street from South Sixth Street to South Center Street (Ward 3)

South Third Street from West Ingledue Street to West Ferner Street (Ward 3)

West Ferner Street from South Third Street to South Center Street (Ward 3)

Highview Drive from West Ingledue Street to cul-de-sac (Ward 3)

Possible End Addition – South First Street from West South Street to West Ingledue Street (Ward 3)

Possible End Addition – South Second Street from West Ferner Street to Columbus Drive (Ward 3)

Milling Planned – July 7-8

Asphalt – Interlayer Lift – July 8-13

Those along or adjacent to the streets being improved, be aware that parking on these streets may not be allowed. These streets are closed to thru traffic during many of the operations, if the road closed sign is up – do not drive through the construction work area. Limited access is being allowed for those that have driveways or for business – school access within the work zone and only when construction equipment is not in the way. For those that do not have space in the driveway that are on the route, the crews are allowing them to park on their yard at risk of damage to the grass. Police Department and Parking Enforcement will not enforce yard parking during the project along these project streets during construction.

Once the interlayer is down, traffic can resume to normal on streets until the asphalt surface comes – which will follow with additional curb and utility work. There may be small elevation changes at the tie-in points. Take it slow. There will be some minor curb and utility adjustments on-going within these work zones – so continue to proceed with extra awareness.

Keep up to date on the latest schedule by checking out the website at: www.marshalltown-ia.gov/858/Construction

Typical working hours are 7 a.m. to 7 p.m., Monday through Friday.