Street Rehab Project update for the coming week

By Times-Republican 3 min read

While this Friday morning's rain may have delayed work, the crews are planning on resuming work on Saturday. The tentative schedule is as follows, but remain flexible – watch for signs on these streets – and be patient as crews work to bring this project to a wrap.

The following sections have been milled, patched and have been covered with the interlayer lift of asphalt. The following is the estimated schedule for the surface lift of asphalt (weather, equipment and progress subject to change these date). Additional curb work and manhole box-out work will follow:

Started July 30, Rained out July 31, Finish Aug. 1

• South Fifth Street from West Main Street to West Nevada Street (Wards 2 & 3)

Aug. 1 & Aug. 3

• South Fourth Street from West Main Street to West Nevada Street (Wards 1, 2, & 3)

• West Nevada Street from South Sixth Street to South Third Street (Ward 3)

Aug. 6 - Aug. 7

• South First Street from West Boone Street to West Church Street (Ward 1)

• South First Street from West Madison Street to West Boone Street (Ward 3)

• West Linn Street from South Third Street to South First Street (Ward 1)

Aug. 7 – Aug. 8

• North Second Street from West State Street to West Lincoln Street (Ward 1)

• West Webster Street from North Second Street to North Center Street (Ward 1)

• West Grant Street from North Second Street to North Center Street (Ward 1)

Aug. 8 & Aug. 10

• West State Street from North 13th Street to North Fifth Street (Ward 2)

The following sections were determined to need additional subgrade work and will be milled full depth, have new stabilized subbase installed and will be paved with three lifts of asphalt in between existing curb and gutter. Additional manhole box-out work is planned during August:

Aug. 3 - Aug. 5

• South First Street from West South Street to West Ingledue Street (Ward 3)

• West Ferner Street, west of South Center Street (WB Lane for ~ 50-ft)

Aug. 4 - Aug. 6

• South Second Street from West Ingledue Street to Columbus Street (Ward 3)

The following sections have been milled, patched and have been covered with two lifts of asphalt. Additional curb work and manhole box-out work is planned during August:

• East Boone Street from South 12th Avenue Place to South 14th Avenue (Ward 1)

• South 14th Avenue from East Nevada Street to East Linn Street (Ward 1)

• South 16th Avenue from East Nevada Street to Norris Place (Ward 1)

• Norris Place from South 16th Avenue to South 17th Avenue (Ward 1)

• South 17th Avenue from Norris Place to East Linn Street (Ward 1)

• South Second Street from West Ferner Street to West Ingledue Street (Ward 3)

• West Ingledue Street from South Sixth Street to South Center Street (Ward 3)

• South Third Street from West Ingledue Street to West Ferner Street (Ward 3)

• West Ferner Street from South Third Street to South Center Street (Ward 3)

• Highview Drive from West Ingledue Street to cul-de-sac (Ward 3)

• East Ferner Street from South Center Street to South Second Avenue (Ward 4)

• South First Avenue from East Anson Street to South Street (Ward 4)

• South First Avenue from East Ferner Street to East Ingledue Street(Ward 4)

The following sections have been milled, new stabilized subbase installed and have been paved with three lifts of asphalt. Additional manhole box-out work is planned during August:

• South First Avenue from South Street to Ferner Street (Ward 4)

Starting at /week.