MARSHALLTOWN HMA STREET REHAB PROJECT
Work continues in the northwest portion of Marshalltown with the Street Rehabilitation project. Expect road closures and find alternative routes.
Residents along or adjacent to the streets being improved, be aware that parking on these streets may not be available. These streets are closed to thru traffic during many of the operations, if the road closed sign is up – do not drive through the construction work area. Limited access is being allowed for those that have driveways within the work zone and only when construction equipment is not in the way. For those that do not have space in the driveway that are on the route, workers are allowing them to park on their yard at risk of damage to their grass. Police Department and Parking Enforcement will not enforce yard parking during the project along these project streets during construction.
Many crews are involved and the schedule will continue to change, especially as weather and pavement conditions may impact it. As of now, the construction teams’ best guess on schedule for those streets in the northwest portion of town in this project includes:
Quadrant 1, Group A:
West State Street from North 13th Street to North Fifth Street (Ward 2)
Milling Planned June 15-16
Clean-Up June 15-17
Patching June 18-19
Asphalt – Interlayer Lift – Week of June 22-26 (depending on condition of other quadrant 1 streets, may be delayed another week if paver needs to follow mill on another stretch)
Quadrant 1, Group B:
North Second Street from West State Street to West Lincoln Street (Ward 1)
West Webster Street from North Second Street to North Center Street (Ward 1)
West Grant Street from North Second Street to North Center Street (Ward 1)
Milling Planned June 17 (weather permitting) or June 18
Clean-Up June 17-19
Patching June 18-19
Asphalt – First Interlayer Lift – Week of June 22-26 (depending on condition of other quadrant 1 streets, may be delayed another week if paver needs to follow mill on another stretch)
Quadrant 1, Group C
South First Street from West Boone Street to West Church Street (Ward 1)
South First Street from West Madison Street to West Boone Street (Ward 3)
West Linn Street from South Third Street to South First Street (Ward 1)
Milling Planned – June 18-19
Patching June 18-19
Asphalt – First Interlayer Lift – Week of June 22-26 (depending on condition of other quadrant 1 streets, may be delayed another week if paver needs to follow mill on another stretch)
Quadrant 1, Group D
South Fourth Street from West Main Street to West Nevada Street (Wards 1, 2, & 3)
South Fifth Street from West Main Street to West Nevada Street (Wards 2 & 3)
West Nevada Street from South Sixth Street to South Three Street (Ward 3)
Milling Planned – June 22-23
Patching June 22-23
Asphalt – First Interlayer Lift – June 22-24
Quadrant 2, Group A
East Boone Street from South 12th Ave. Place to South 14th Ave. (Ward 1)
South 14th Ave. from East Nevada Street to East Linn Street (Ward 1)
Curb Spot Repair June 16-19
Milling Planned – Mid-to-Late Week of June 22-26
Quadrant 2, Group B
South 16th Ave. from East Nevada Street to Norris Place (Ward 1)
Norris Place from South 16th Ave. to South 17th Ave. (Ward 1)
South 17th Ave. from Norris Place to East Linn Street (Ward 1)
Curb Spot Repair June 16-19
Milling Planned – Mid-to-Late Week of June 22-26
Surface lift of asphalt will come after all interlayer lifts are complete.
Keep up to date on the latest schedule by checking out website: www.marshalltown-ia.gov/858/Construction
Typical working hours will be 7 a.m. to 7 p.m., Monday through Friday.